Cost Estimate

June 2010

Juan de Fuca, with the Coho

With the selection of the McLoughlin Option and pending the submission of an amendment to the Core Area Liquid Waste Management Plan, a revised cost estimate is now available for the Core Area's new wastewater system.

  • The cost of the system is estimated $782 million.
  • Annual resource recovery revenues are estimated at $3.1 million by 2030.
  • Annual operating costs for the system are estimated at $14.5 million per year, with a per household cost of $210-$500 per year, depending on the municipality and structure of cost sharing agreements.

With these initial estimates, the CRD will now move forward with procurement options and cost sharing agreements.

Fall 2009

Cost Estimates for Option 1A & 1B

Cost estimates for Options 1A are significantly lower than previously thought. Breakdowns are as follows.

Option 1A $965 million
Option 1B $875 million

For more information on Options 1A, please see the siting page.

Summer 2009

Cost Estimates for the Three Wastewater Treatment Strategies

The chart below details the cost projections (escalated to the mid-point of construction) for the three distributed wastewater treatment plan scenarios. Read more on the details of each option on the Siting page.

Capital Costs

2009 Cost Estimate for Three Options

Operating Costs, Revenue and Greenhouse Gas Costs

Operating costs, revenue and greenhouse gas costs

As the number of wastewater treatment plants increase, the overall capital costs increase significantly. This is primarily due to the loss of economies of scale; larger plants are less expensive to build on a unit cost basis compared to smaller plants. The potential annual revenue from resource recovery increases with the number of plants, although the relative increase significantly slows with additional facilities. The data show that operations and maintenance costs are significantly larger than the potential revenues. Options 2 and 3 benefit from additional greenhouse gas credits.

2009 Capital Cost Estimate Breakdown

Capital costs for wastewater treatment are calculated on:Fort Rodd Hill Lighthouse

  • Base construction costs
  • Design and construction contingencies
  • Indirect costs (engineering, administration, miscellaneous and interim financing)

Once the CRD has established a direction, it is important that the capital costs, particularly in the first stage, be inflated to reflect the actual period of construction. Costs for wastewater treatment are shown in 2008 dollars.

 
Cost ($ Million)
Facility
Option1
Option 2
Option 3

Wastewater Treatment

Macaulay/McLoughlin Point WWTP
Clover Point Wet Weather Plant
Saanich East WWTP
West Shore WWTP
James Bay/ Downtown WWTP
Juan de Fuca WWTP
Oak Bay WWTP
Westhills WWTP
Florence Lake WWTP
Esquimalt/View Royal WWTP
Town and Country WWTP

 

454
171
141
152

 

370
165
141
54
410
164

 

263
165
146
51
247
174
152
92
56
62
189

Wastewater Conveyance

Modifications

 

68

 

87

 

54

Biosolids Drying

Hartland Biosolids Drying Facility

 

53

 

53

 

53

Organics

Royal Roads Organics Facility

   

 

67

Total Capital Costs
1039
1444
1771
Escalation Cost (see Note)
131
182
223
Total Estimated Capital Costs
1170
1626
1994

 

Note: capital costs are escalated from 2008 dollars to the expected mid point of construction using an inflation allowance of 2.0% per year

2008 Cost Estimates for Municipalities (based on 1.2 billion)

In 2008, the CRD calculated illustrative cost scenarios for residents of each municipality in the core area, to provide a projection of potential costs of wastewater treatment. The total capital cost of 1.2 billlion was used. An update of this estimate is expected in 2009. As with any projections, the costs were based on current information, and are subject to a number of assumptions, including:

  • Capital and operating cost estimates from consulting engineers' current multi-treatment plant model
  • No development cost charge funding
  • No current cost sharing agreement
  • Allocation of costs between municipalities based on the most recent engineering projections
  • Borrowing at 6% over 25 years at an inflation rate of 2.5%
  • Projections for population and assessment of growth
Cost Sharing

Cost sharing formulas have not been implemented in the numbers below. Cost sharing negotiations are the responsibility of individual municipalities and would occur before final costs can be known.

The CRD has retained an independent fairness and methodology advisor, Peter Adams, to assist in determining cost sharing options available to municipalities.

2008 Costs to Average Residential Household Per Year

Municipality
Dry Weather Flow
Total Flow
Colwood $220.71

$197.81

Esquimalt $368.76 $408.45
Langford $188.70 $157.49
Oak Bay $541.11 $712.98
Saanich $548.35 $471.12
Victoria $412.59 $464.85
View Royal $499.33 $430.88

*This estimate is based on 2007 construction costs on a total capital cost of 1.2 billion

© Top image courtesy of Evan Leeson.